MAN-DAY CAPABILITY
Contingency Operations
References:
NAVFAC P-437, Planning Guide for Navy Facilities, Vol. 1
NAVFAC P-437, Planning Guide for Navy Facilities, Vol. 2
NAVEDTRA 12543, Naval Construction Force/Seabee 1 &C
Seabee Crew Leader Handbook
Seabee Construction Management I & II
Abbreviations
MC = Total Manday Capability of Direct Labor Personnel (projects + training)
DL = Number of Direct Labor Personnel Assigned
WD = Number of Available Workdays in the Deployment
ME = Manday Equivalent (converts typical workdays to 8 hour mandays)
AF = Availability Factor
Manday Capability
In order to calculate the construction activity duration's, you must first understand the Manday Capability Equation.
The equation used to determine the direct labor manday capability at the mainbody site and each detail site is as follows.
Manday Capability (MC)- the total number of mandays that a NMCB, DET, DFT, etc. is able to produce within a specified period of time.
Direct Labor personnel are those whose efforts contribute to project work-in-place (WIP).
Indirect labor personnel provide project support and include mechanics, expeditors, EA’s (except when surveying), MLO / CTR, Staffs and the Ops / QC staff.
Overhead labor personnel provide battalion support such as disbursing, galley ops, personnel, admin and supply.
Workdays
Workdays (WD) - The number of available workdays is the total number of calendar days minus all off days.
Off days may include: Sundays; half of the Saturdays; all holidays; battalion turnover (up to 10 days for mainbody); one day for mid-deployment party; and one day for the change of command.
Manday Equivalent (ME) - is the actual manhours worked “swinging hammers” on the job site during a workday. It is the length of the workday, minus lunch, minus breaks minus ravel time to and from the job site (including lunch), divided by 8 (the number of hours in a manday).
Availability Factor (AF)- Takes into account that Seabees assigned as direct labor are not available 100% of the time.
About 20% of the direct labor personnel’s time is lost to : leave, liberty, inspections, quarters, medical, dental, haircuts, military drills, battalion indoc, watches, collateral duties, etc.
Availability Factors for planning purposes are provided by higher headquarters.
They vary between .60 and .90 depending on the deployment site.
The typical percentages are .75 for mainbody sites and .85 for detail sites.
The typical percentage for contingency construction is .90.
Example #1
How many Mandays of construction can a det with 60 direct labor personnel do in a deployment with 150 workdays, an availability factor of .80 and a manday equivalent of 1.125?
Answer #1
MC = DL x WD x ME x AF
MC = 60 x 150 x 1.125 x .80
MC = 8,100
Example #2
How many Direct Labor personnel would be required for a detail tasked to do 4,000 mandays in a deployment with 150 workdays?
Use 1.125 as the manday equivalent and .90 for the availability factor.
Answer #2
DL = MC / (WD x ME x AF)
DL = 4,000 / (150 x 1.125 x .90)
DL = 4,000 / 151.875
DL = 4,000 / 151.875 = 26.337 or 27
Example #3
How many Workdays would it take for 70 direct labor personnel to do 3,150 mandays of construction with an availability factor of .75 and a manday equivalent of 1.125?
Answer #3
WD = MD / (DL x ME x AF)
WD = 3,150 / (70 x 1.125 x .75)
WD = 3,150 / 59.0625
WD = 53.33 or 54
Example #4
What would our Manday Equivalent be if we had a crew of 12 working from 0630 to 1700, traveled 5 minutes to and from work, 1 hour for lunch (including travel time) and two 10 minute breaks?
Answer #4
ME = WD - Travel time - break time -lunch / 8
ME = 10.5 - .167 - .33 - 1 / 8
ME = 1.125
Example #5
If a crew of 8 reported 125 mandays direct labor in a month with 21 workdays and a manday equivalent of 1.125, what was the actual Availability Factor?
Answer #5
AF = MD / (DL x WD x ME)
AF = 125 / (8 x 21 x 1.125)
AF = 125 / 189
AF = .6613756 or 66%
SMEAC
Situation
Mission
Execution
Administration
Command and control
SMEAC #1
Situation: Dayton peach accord requires deployment to NATO forces to Bosnia to which the United States has committed 5,000. Permanent and temporary campsites are required to house U.S. Forces.
Mission: Construct campsite to house JTF forces. Construct one (1) 750 man tent camp. Provide for repair of runway for C-130 aircraft. Convoy security will be provided by JTF as requested.
Execution: Be prepared to deploy with in 5 days, advise ALCON when available for airlift. Provide specific airlift/sealift requirements to 2NCB within 48 hours. Identify Class IV materials required for camp construction within 72 hours. Upon completion of tasking, redeploy to originating site (approx. 60 days).
Administration: Operate own self-sufficient camp. Resupply requests through JTF. CESE support through own command, require anticipated schedule for airlift within fire days of arrival.
Command and control:
OPCON - JTF
ADCON - NMCB 74
Advise ADCON on arrival
Revise schedule for construction and submit weekly sitrep.
CONVERT MANHOURS TO MANDAYS
MD = MH / 8 hour in a workday
MD = 7,501 / 8
MD = 937.625 or 938
FORMULA FOR MANDAY CAPABILITY
DL = MD / WD / ME / AF
DL = 938 / 56 (60 - 4 days for mount out) / 1.5 / .90
DL = 10.049 or 10
RATIO
CM 6 TO 1
WILL BE CHANGING TO 8 TO 1 BUT IT HAS NOT GONE INTO EFFECT YET
HM 100 TO 1
IDC 150 TO 1
YN/PN 50 TO 1
MS 50 TO 1 LESS THEN 50 PEOPLE THERE WILL BE NO FSA’S
SK UNDER 100 THERE WILL BE ONLY 1
ET DEPENDS ON SMEAC
GM DEPENDS ON SMEAC
FSA
FOR EVERY ONE MS THERE WILL BE ONLY ONE FSA’S
1 TO 1
RRR
46 LEVEL I
20 LEVEL II
6 CRETE MOB.
TOTAL
72 PEOPLE
MAIN SUPPLY ROUTE
MSR
6 EO’s
FOR EVERY 10 MILES OF ROADS
SECURITY
SECURTY PLT HAS 45 PEOPLE
PLT COMMANDER
ASST. PLT COMMANDER
RIGHT GUIDE
14 IN SQ
WATER WELL
TOTAL OF 21 PEOPLE
OIC
MS
IDC
18 DL